(I) Installation method
1. Clean the surface and polish and remove the dust. In order to ensure the paste effect of ceramic pieces, we need to fine polish the paste position of the pipe before installation, remove rust, and clean the surface with alcohol and other dilutions to ensure that the surface is clean.
2, with glue coated with glue. Prepare viscose according to the proportion, use within half an hour as far as possible, and must stir fully before use to ensure that all ingredients are fully mixed. When applying glue, daub evenly, and paste surface and side should be coated with glue, not leakage glue phenomenon.
3, pasting and curing. After the smear, the porcelain should be pressed tightly and the gap between the tiles is filled. After the paste, the porcelain should be solidified for 24-48 hours before use.
(2) Matters needing attention
1. In the process of handling and installation of wear-resistant ceramic patch pipes, it is necessary to take them gently and put them gently to avoid violent collision and avoid damage to the end surface caused by hard objects hitting the ceramic end surface.
2. When installing the wear-resistant ceramic patch pipeline, the center line of the ceramic pipe should be aligned with the center line of the pipeline to be connected, and the connecting part should be carefully high and flat to ensure that the two ends are accurate, and the dislocation of the end surface should be controlled within 1 mm.
3, the internal porcelain method and fixation method of the wear-resistant ceramic patch pipe determines that it has strict direction, the installation of the wear-resistant ceramic patch pipe in accordance with the technical requirements of the conveying fluid and the connection gap direction, reasonably reduce pipe erosion and wear.
4, wear-resistant ceramic patch pipeline mostly transport powder, gas and liquid and other fluids, in order to ensure the safety of transportation, in the installation also need to strictly check the sealing of the connection, in order to prevent fluid leakage.
5, Flange protection, in order to prevent the transportation and storage of the flange rust or wear process, we need to grease the flange, and cover the protective cap.
6. Wear-resistant ceramic patch pipes should be numbered according to the drawings to avoid errors in the production and installation process.
7. In the process of installing wear-resistant ceramic patch pipes, it should be installed from both ends to the middle, so that it is convenient to adjust. The cumulative error also needs to consider in the installation, which should be eliminated through the pipeline adjustment before the installation.
8. In order to increase the firmness of the flange connection, try to weld the hanging ear at the port position of the wear-resistant ceramic patch pipe.
Construction Technology And Precautions For Wear-resistant Ceramic Patch Pipe
Oct 09, 2023
Send Inquiry
Latest News
Contact Us
- Mob: +8615053412502
- Email: Hongsheng@hsmachineryparts.com
- Add: Bohai Road, Sub-District Office, Qingyun County, Dezhou City, Shandong Province