Hydrostatic Test Of Ductile Cast Iron

Jul 18, 2023

1. Water injection into the pipe should be injected slowly from the downstream. During water injection, an exhaust valve should be set at the top of the pipe and the high point of the upstream of the test pipe section to remove the gas in the pipe.
2. The length of the pipe section for the hydraulic test should not be greater than 1.0km.
3. The back of the test pipe section shall comply with the following provisions:
3.1 The back should be set on the original soil or artificial back, and reinforcement measures should be taken when the soil is soft;
3.2 The back wall shall be flat and perpendicular to the axis of the pipe.
4. The following provisions shall be met before the hydrostatic test:
4.1 Pipeline installation and backfilling of trenches shall meet the requirements of the specification;
4.2 The support piers and anchorage facilities of pipe fittings have reached the design strength; the pipe fittings without branch piers and anchorage facilities shall be strengthened;
4.3 All the openings of the test pipeline shall be strictly blocked, and no water seepage shall be allowed;
4.4 The gate valve shall not be used as the blocking board for the test pipeline, and shall not have the fire hydrant, water hammer remover, safety valve and other accessories;
4.5 The debris in the pipeline shall be removed before the hydraulic test.
5. After the test pipe section is filled with water, it is advisable to conduct the hydraulic test to be fully soaked under no greater than the working pressure, and the soaking time should be more than 24 hours.
6. Test pressure
Working pressure is 0.5MPa, and the test pressure is 2.0 times of the working pressure;
Working pressure is> 0.5MPa, and the test pressure is working pressure plus 0.5MPa.
7. Test method
7.1 Pre-test stage: raise the water pressure in the pipe slowly to the test pressure for 30min. During the period, fill the pressure, but not be higher than the test pressure; check for leakage and damage at the pipe interface and fittings; when water leakage and damage, stop the pressure test in time and determine the reason and take the corresponding measures.
7.2 Main test stage: after stopping water injection and pressure, stabilize for 15min; When the pressure drop after 15min does not exceed 0.03MPa, the test pressure is reduced to the working pressure for 30min. If there is no leakage, the hydraulic test is qualified.
8. Acceptance of hydraulic test
For the final qualification determination basis, the measured water seepage shall be less than or equal to the allowable value specified in the following table and the allowable value specified in the following formula: